# CAIN-A75-043 Physical Schedule Assurance Review

**Verdict:** VERIFIED

> Recomputes a construction schedule: coverage, duration arithmetic, precedence, cure gaps, permits, deadline and claim honesty. It does not visit the site.

| Project | Verdict | Tasks | Deadline | Failed checks |
|---|---|---|---|---|
| 0 SITE-7 | SOUND | 3 | 20.0 |  |

## What this proves and what it does not
- Proves: every task appears once, start/finish matches duration, predecessors finish before successors, cure gaps are respected, permits cover the work window, and everything finishes by the deadline.
- Does not prove: that durations are realistic, that the site is ready, or that weather and inspections will not delay the plan. It is a schedule-record review.
- Verify offline: `python3 verify_offline.py run.json --pinned-key aMIQLoi7VBHeihmxQOXxaTGZZ2YPyDfZFCvIfwiTfYg=`